QUESTION 70

Drag and Drop Question

A company is outsourcing its support operations to an external service provider and plans to complete the project by April 1.

- The external Support engineers must have the ability to power cycle,

create, and edit virtual machines settings within their assigned vSphere site.

- The company maintains three vCenter servers in Enhanced Linked Mode

that are run as virtual machines in the supported infrastructure.

- The vCenter servers will be supposed by the external service provider.

- Each vCenter server is connected to its own local Platform Services Controller and MSSQL database server.

- The company will provide escalation support and physical access on a per request basis.

- 99.9% ESXi host uptime is required in this environment, but no SLA has been specified for the hosted applications.

Hidden Content

    Give reaction to this post to see the hidden content.

  • Like 2

Share this post


Link to post
Share on other sites

Risk --> Missing the April 1 deadline...

Constraint --> Remote support...

Assumption --> The company is...

Requirement --> The SLA allows for..

Share this post


Link to post
Share on other sites

Risk --> Missing the April 1 deadline...

Constraint --> Remote support...

Assumption --> The company is...

Requirement --> The SLA allows for..

 

Hi guys,

I think that is incorrect.

I believe it should be:

Risk --> Missing the April 1 deadline...

Constraint --> The SLA allows for..

Assumption --> The company is...

Requirement --> Remote support...

 

What do you think?

Edited by vmadmin93

Share this post


Link to post
Share on other sites

Risk --> Missing the April 1 deadline...

Constraint --> Remote support...

Assumption --> The company is...

Requirement --> The SLA allows for..

 

 

Lets break this down....

 

 

 

A company is outsourcing its support operations to an external service provider and plans to complete the project by April 1. <---- the key word in here is outsourcing its support operations,

 

 

Risk --> Missing the April 1 deadline... - Yep, this needs to be done by April 1.

Constraint --> Remote support... - This outsourcing support will have the power to perform some VM operation, this constrains our decisions since someone external will be working on the customer's scenario. think of it as a support contact..,

Assumption --> The company is... - "The company will provide escalation support and physical access on a per request basis" will it? this needs to be validated and confirmed so here is an assumption.

Requirement --> The SLA allows for.. Even though the SLA has not been established per the question's statement the ESXi uptime needs to be 99.9% which is translated to 8h 45m 57.0s per year of downtime.

Share this post


Link to post
Share on other sites

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

Sign in to follow this  

×
×
  • Create New...